Project Scope: The improvements consisted of street and sidewalk improvements along the west side of Pearl Street from the Garner Baseball Complex frontage to Main St and improvements along Parker Street from the eastern boundary of new townhomes to N Montague Street. This project included road widening, addition of on-street parking, curb and gutter and sidewalk. Along with the nearby development, Pearl Street Townhomes, this capital project completed the road and pedestrian network in the area. Pearl and Parker_Before and After
Funding Source: 2021 Street and Sidewalk Improvement Bonds
Design Consultant: Kimley-Horn Associates
Contractor: Fred Smith Company
Current Status (updated January 2026): Construction is complete.
Project Schedule:
| 90% Design | Completed Spring 2024 |
| Real Estate Acquisitions | Completed Fall 2024 |
| Utility Relocation | Completed Early Winter 2025 |
| Final Bid Documents | Completed Spring 2025 |
| Bidding | April 14, 2025 to May 13, 2025 |
| Construction Start | July 21, 2025 |
| End of Construction | December 2025 |
Town Project Manager: Lisa Rodriguez