Project Scope: The improvements consisted of street and sidewalk improvements along the west side of Pearl Street from the Garner Baseball Complex frontage to Main St and improvements along Parker Street from the eastern boundary of new townhomes to N Montague Street. This project included road widening, addition of on-street parking, curb and gutter and sidewalk. Along with the nearby development, Pearl Street Townhomes, this capital project completed the road and pedestrian network in the area. Pearl and Parker_Before and After

Funding Source: 2021 Street and Sidewalk Improvement Bonds

Design Consultant:  Kimley-Horn Associates

Contractor:  Fred Smith Company

Current Status (updated January 2026): Construction is complete.

Project Schedule:

90% Design Completed Spring 2024
Real Estate Acquisitions Completed Fall 2024
Utility Relocation Completed Early Winter 2025
Final Bid Documents Completed Spring 2025
Bidding April 14, 2025 to May 13, 2025
Construction Start July 21, 2025
End of Construction December 2025

 

Town Project Manager: Lisa Rodriguez