Main Street ParkingPhoto Description: The above image shows an aerial view of the project area.

Project Scope: This project adds 39 angled parking spots along Main Street from N Montague Street to Purvis Street and pedestrian crosswalks at each end.  

Funding Source: 2021 Street and Sidewalk Improvement Bonds

Design Consultant:  Kimley-Horn Associates

Current Status (updated May 2026): Lanier Construction was awarded the construction contract. The NCRR Right of Entry application is under review. 

Project Schedule (tentative and subject to change):

90% Design Completed Spring 2025
NCRR Review In Progress
Final Bid Documents Pending NCRR Approval
Bidding January 2026
NCRR Right of Entry Spring 2026
Begin Construction Pending NCRR Right of Entry

 

Town Project Manager: Branyun Bullard